NAUTICA FINANCIAL SERVICES​
  • Home
  • Marine Services
    • Consulting Services
    • Build / Lease Program
    • Construction Financing >
      • Jensen / Nautica
      • Vessel Build Program
      • Milestone Schedule
      • Loan Proposal
      • Lease Proposal
      • Public Private Partnerships
      • Funding Process
    • Loan and Lease Options
    • Recent Vessels Financed
    • Vessel Brokerage
    • Nichols Marine Services
    • Clients
  • Our Team
  • Contact
  • Energy Sector
    • Insurance Diagram >
      • Loan Structure
      • Funding Process
    • Risk
  • Home
  • Marine Services
    • Consulting Services
    • Build / Lease Program
    • Construction Financing >
      • Jensen / Nautica
      • Vessel Build Program
      • Milestone Schedule
      • Loan Proposal
      • Lease Proposal
      • Public Private Partnerships
      • Funding Process
    • Loan and Lease Options
    • Recent Vessels Financed
    • Vessel Brokerage
    • Nichols Marine Services
    • Clients
  • Our Team
  • Contact
  • Energy Sector
    • Insurance Diagram >
      • Loan Structure
      • Funding Process
    • Risk

Milestone Payment schedule - Example

Based on $10 million contract, and 10-month construction projection
 
5%            ($500,000) due upon delivery of Notice to Proceed 
 
10%          ($1.000,000) upon completion of below: approx. 15 days after a contract signing.
40% Metal ordered 
Deposits on 90% of long lead Builder furnished items 
 
10%          ($1,000,000) upon completion of below: approx. 31 days after a contract signing.
Deposits and purchase orders complete on all major components. 
90% of Metal has been ordered 
10% of N.C. Cutting complete 
Start of vessel construction. 
 
10%          ($1,000,000) upon completion of below: approx. 61 days after a contract signing.
40% of Structural Metal received at Builder site 
25% of N.C. Cutting complete 
10% Hull frames and bulkheads erected 
 
10%          ($1,000,000) upon completion of below: approx. 92 days after a contract signing.
20% of Hull structure complete 
15% of House structure complete 
15% of Welding complete 
80% of N.C. Cutting complete 
95% of Metal received. 
 
10%          ($1,000,000) upon completion of below: approx. 128 days after a contract signing.
45% of Hull structure complete 
30% of House structure complete 
30% of Welding complete 
99% of N.C. Cutting complete. 
 
10%          ($1,000,000) upon completion of below: approx. 172 days after a contract signing.
70% of Hull structure complete 
65% of House structure complete  
60% of Welding complete 
20% of all systems complete 
10% of Joiner complete 
10%          ($1,000,000) upon completion of below: approx. 206 days after a contract signing.
95% of Hull structure complete 
85% of House structure complete 
80% of Welding complete 
Main engines, auxiliary engines and drive units set in hull 
50% of all systems complete 
50% of Insulation complete 
30% of Joiner complete. 
 
10%          ($1,000,000) upon completion of below: approx. 245 days after a contract signing.
Hull structure completed 
House structure completed 
70% of all systems complete 
80% of Insulation complete 
60% of Joiner complete 
95% of Main engines, auxiliary engines and shaft installation complete. 
 
10%          ($1,000,000) upon completion of below: approx. 275 days after a contract signing.
90% of all systems complete 
99% of Insulation complete 
85% of Joiner complete 
​
5%            ($500,000) upon vessel acceptance and delivery, approx. 307 days after a contract signing.

Quick LInks

Home
Our Clients
Legal
Our Team
Contact

Services

Services​
Loans/Leases
Construction Finance
Build/Lease
​Nichols MS
Public Private Partnership
​​Consulting Services
Municipal Financing
Brokerage and Remarketing
© COPYRIGHT 2017. ALL RIGHTS RESERVED.